Energy Vault Closes $78 Million Financing for 300 MWh Texas BESS

Key Facts
  • Financing closed: $78 million
  • Storage capacity: 300 MWh
  • Total investment: $100 million
  • Preferred equity to repay bridge loan: $80 million
  • Tax revenue over 10 years: $9.3 million
  • Construction jobs: 65 local jobs

Energy Vault closed $78 million in non-recourse construction and bridge financing for the SOSA Energy Center, according to ESS News. The site is a 150 MW and 300 MWh battery energy storage system under construction in Madison County, Texas. ESS News reported that the two-hour duration facility represents an approximately $100 million total investment. Construction started in the fourth quarter of 2025. Energy Vault targets commercial operations in the third quarter of 2027.

The project is the first energy storage asset placed into development under Asset Vault, according to ESS News. Asset Vault serves as the company platform for owning and operating storage and data center power infrastructure. Mercom Capital reported that an $80 million preferred equity investment will repay the bridge loan upon project completion. The preferred equity commitment was secured prior to the debt closing.

Energy Vault stated that three funding sources will support the build, according to Mercom Capital. Construction financing, the preferred equity investment, and a draw on the OIC preferred facility will fund the project. The company structured the package to reach commercial operations on a non-recourse basis. Asset Vault president Cory Magnuson stated that a bank, a strategic partner, and an institutional investor backed SOSA on those terms.

Energy Vault self-performs engineering, procurement, and construction for the Madison County facility, according to ESS News. Workers have completed civil work at the site. Crews have also installed the project substation. Major equipment is scheduled to arrive on site in the coming months, according to ESS News.

Once completed, the storage facility will operate on a merchant basis in the ERCOT North market, according to Mercom Capital. The Electric Reliability Council of Texas site will supply power and ancillary services. Energy Vault indicated it remains flexible regarding revenue strategy, according to ESS News. The company stated it retains the option to enter a contracted offtake agreement as market conditions evolve.

Energy Vault projects that the asset will deliver $250 million to $300 million or more in long-term revenues, according to ESS News. The company expects the facility to generate recurring EBITDA margins of 65% to 75%. ESS News noted that these targets align with broader Asset Vault portfolio goals.

The battery facility will provide local economic contributions in Madison County, according to Mercom Capital. Energy Vault estimates the asset will generate $9.3 million in tax revenue over 10 years. That tax revenue will support the North Zulch Independent School District and Madison County. Mercom Capital reported that construction will also create 65 local jobs.

Why It Matters

SOSA Energy Center is the first storage project placed into development under the Asset Vault model. The financing blends construction debt, preferred equity, and a draw on the OIC preferred facility. Energy Vault said that package is intended to fund the project through construction and commercial operations without recourse to the parent company.

The project also expands two-hour merchant battery capacity within the ERCOT North market. Operating on a merchant basis allows the 150 MW / 300 MWh system to capture power and ancillary services revenue. Energy Vault pairs that merchant exposure with the option to sign an offtake contract if market conditions change. Energy Vault targets EBITDA margins of 65% to 75% for the asset. The project also provides $9.3 million in local tax revenue over 10 years. The project anchors the company push to own and operate energy storage and data center power assets.

Critical Perspective

Although Energy Vault closed $78 million in non-recourse construction and bridge financing for the 150 MW system, according to ESS News, building on a merchant basis leaves the project vulnerable to ERCOT price crashes. Energy Vault projects that the asset will deliver $250 million to $300 million or more in long-term revenues, according to ESS News, but capturing those merchant revenues requires sustained market volatility that battery additions could erode. Mercom Capital reported that an $80 million preferred equity investment will repay the bridge loan upon project completion, creating substantial pressure to deliver cash flows immediately after commissioning. Can the asset generate sufficient revenue in ERCOT North to support this complex financing structure without a guaranteed power purchase contract?

Sources

Related Coverage

On the Ground
StageUnder Construction