Public Input Opens on BECI, a $1.2 Billion 765 kV Line Running 190 Miles Across Southern Wisconsin

Key Facts
  • Investment: $1.2 billion
  • Line Length: About 190 miles
  • Voltage: 765 kV
  • Public Comment Deadline: September 7, 2026
  • Target In-Service: 2034

Listen to this article

Midcontinent Grid Solutions opened public input on August 5, 2026 for the BECI transmission project in Wisconsin. The line runs about 190 miles at 765 kV, from Crawford County in the southwest to Walworth County near the Illinois border. The developer puts the investment at $1.2 billion. Midcontinent Grid Solutions is a 50/50 joint venture between Transource Energy and BHE Transmission.

The full name of the project traces the route. BECI stands for Bell Center to Columbia to Sugar Creek to the Illinois and Wisconsin state line. MISO selected the developers through its competitive transmission process and issued the selection report on January 6, 2026. The developers target an in-service date of 2034.

What Happens Next

Eight public open houses run through August 2026. Midcontinent Grid Solutions also opened a virtual open house and an online comment card. Written comments close on September 7, 2026. The company plans to file its application for a Certificate of Public Convenience and Necessity with the Public Service Commission of Wisconsin in early 2027.

No final route exists yet. That is the point of the current phase. Landowners and local governments respond to route segments now, before the CPCN application locks the corridor. Once the filing lands at the PSCW, the argument shifts from where the line goes to whether it gets built at all.

Where BECI Sits in the Portfolio

BECI comes out of the MISO Long Range Transmission Planning Tranche 2.1 portfolio, which the MISO board approved in December 2024. Tranche 2.1 holds seven competitive projects. MGRID covered two of them in May 2026, when MISO awarded an Ameren-led consortium 237 miles of 765 kV line across Illinois for an estimated $1.658 billion.

Laura Rauch, MISO Executive Director of Transmission Planning, says the Tranche 2.1 portfolio returns benefits of 1.8 to 3.5 times its cost. That ratio is a planning estimate, not a settled number, and it carries the whole ratepayer case for the portfolio.

Why It Matters

Siting is the schedule risk on 765 kV, not steel or money. A 190-mile corridor across southern Wisconsin crosses farmland, and the PSCW record on contested routes runs long. The developers have set 2034 for service, eight years out from a project that has not yet picked a route or filed for a certificate. That gap is the honest measure of how slow high-voltage buildout still is.

The cost-benefit ratio deserves the same scrutiny. A range of 1.8 to 3.5 is wide enough to cover very different outcomes for Wisconsin ratepayers. The value depends on load growth arriving as forecast between now and 2034. Interested parties should press for the load assumptions behind that range during the comment window, because after the CPCN filing the planning case is much harder to reopen.

Critical Perspective

Midcontinent Grid Solutions has set 2034 for a 190-mile 765 kV line that has no route and no CPCN application on file until early 2027. The 1.8 to 3.5 times benefit ratio MISO attaches to the Tranche 2.1 portfolio is a planning estimate, and it carries the ratepayer case for a $1.2 billion line whose corridor nobody has drawn. Grain Belt Express spent more than a decade in Missouri and Kansas proceedings, lost a Missouri Public Service Commission decision, refiled, and reached construction only after the route fight outlasted two owners. If southern Wisconsin farmland produces the same kind of record, does 2034 describe the schedule or the earliest date the developers are willing to print?