Latitude Intelligence Tracks 120 GW of Signed Data Center Load as Midterms Bring New Scrutiny
- Signed data center load in tracked utility territories: 120 GW
- Data center load operating today: 22 GW
- Georgia Power signed load pipeline: 12.8 GW
- NIPSCO signed pipeline vs. current peak load: 169%
- Dominion dispatchable generation sought: 7.3 GW
- Average time from announcement to first power: 33 months
Utilities across the territories Latitude Intelligence tracks have 120 GW of signed data center load, compared with 22 GW currently operating. In Georgia, Georgia Power’s signed pipeline totals 12.8 GW. Grid operators face November 16 deadlines to respond to federal large-load orders.
Latitude Intelligence puts signed load at around 5.5 times operating data center load across its tracked footprint. Reported data center load is about 4.5 times the signed total.
The Federal Energy Regulatory Commission’s large-load show-cause orders require responses from the regional grid operators. According to Latitude Media, the November 16 deadline applies to five operators. SPP’s response is due November 20.
Georgia and Ohio Put Expansion Under Scrutiny
Georgia Power’s reported load totals 80.1 GW, against the 12.8 GW signed pipeline counted by Latitude Intelligence. Latitude Media reports that Georgia’s incoming utility commissioners plan to scrutinize the utility’s gas-heavy expansion. They have also signaled attention to its frequent rate increases.
In Ohio, voters favored restrictions in all 21 local data center-related measures considered during the midterms, according to Latitude Media. A proposed constitutional amendment would prohibit construction of certain data centers statewide. Supporters are gathering signatures for a possible ballot appearance next fall.
AEP Ohio has the most signed load among the territories Latitude Intelligence tracks. Elsewhere, NIPSCO’s signed data center pipeline equals 169% of its current peak load in Indiana. PPL’s pipeline equals 145% in Pennsylvania.
Utilities Pursue More Generation
Dominion is seeking up to 7.3 GW of dispatchable generation, Latitude Media reports. Final submissions are due December 18, with in-service dates extending through 2036.
Georgia Power is pursuing another 2 to 6 GW of capacity. AEP has disclosed separate solicitations of 4 GW each for Indiana Michigan Power and Public Service Company of Oklahoma. Xcel also has multi-gigawatt procurements underway across its regions, according to Latitude Media.
J.P. Morgan expects Democratic victories in states central to AI infrastructure growth to slow permitting and raise project costs. Its analyst Tarek Hamid expects more focus on international data center development. He said the United States is becoming less hospitable to development.
Why It Matters
The development timetable already stretches across years. Latitude Intelligence’s sample of 14 data center projects energized since late 2021 shows an average of 33 months from announcement to first power. That is just under three years.
Utilities are pursuing additional generation while incoming Georgia commissioners prepare to examine expansion plans and Ohio voters back restrictions. Dominion’s December 18 submission deadline puts a concrete next step on that procurement calendar.
Critical Perspective
Latitude Intelligence tracks 120 GW of signed data center load across utility territories, compared with only 22 GW currently operating. Latitude Media reports that voters in Ohio backed restrictions in all 21 local data center measures during the midterms, signaling that local communities will not quietly absorb this sudden growth. At the same time, Dominion is seeking up to 7.3 GW of dispatchable generation, according to Latitude Media, setting up a sharp conflict with ratepayers who face the risk of expensive plant construction. How many signed data center commitments will utilities be forced to abandon if incoming regulators block proposed power plants and local ballots halt facility construction?