e-STORAGE to Supply 1.43 GWh of Batteries for X-ELIO Projects in Texas and Australia

Key Facts
  • Total Storage Capacity: 1.43 GWh
  • Total Power: 590 MW
  • Service Agreement Term: 22-year
  • Largest Project (Texas): 200 MW / 482 MWh
  • SolBank 3.0 Unit Capacity: 5 MWh

X-ELIO has selected Canadian Solar’s e-STORAGE to supply battery energy storage systems for five projects across the US and Australia. Four of the projects are in Texas and one is in New South Wales. The supply agreements total 590 MW of power and 1.43 GWh of DC storage capacity, ESS News reported.

X-ELIO is a Spanish clean energy developer owned by Brookfield Renewable. e-STORAGE is an Ontario-based subsidiary of Canadian Solar. The two companies signed the agreements at RE+ 2026 in the US, according to ESS News.

Canadian Solar said shipments were already underway. It expects the projects to reach commercial operation in 2027 and 2028. Each supply agreement includes a 22-year long-term service agreement, so e-STORAGE will stay responsible for service on the batteries long after delivery.

All five projects will use e-STORAGE’s SolBank 3.0 product. Canadian Solar said the units are built with battery cells manufactured at its own facilities. e-STORAGE will also supply power conversion systems and plant controls for each site.

Each SolBank 3.0 unit has a nominal capacity of 5 MWh, according to ESS News. The product supports 2-hour and 4-hour configurations. Its rated power output ranges from 1.2 MW to 2.35 MW.

The largest of the five is a 200 MW / 482 MWh installation in Texas. Canadian Solar said it will run on EQ-S, the proprietary energy management system that e-STORAGE developed in North America. The other four projects will use the same SolBank 3.0 batteries.

e-STORAGE President Jeff Roy said the deal marks the beginning of a global partnership with X-ELIO, according to Interesting Engineering. The agreements cover projects on two continents, which gives the partnership an early footprint in both the US and Australian markets.

Why It Matters

Canadian Solar says the batteries will shift midday solar output into the evening peak in both markets. In Texas, the systems target the state’s tightest supply hours after sunset. In New South Wales, the company says the same shift will support coal retirement goals.

For grid planners tracking evening supply, the milestone to watch is commercial operation. Shipments are already underway, and Canadian Solar expects the five projects to enter service in 2027 and 2028. The 22-year service agreements extend e-STORAGE’s role well past that point.

Critical Perspective

ESS News reported that the supply agreements total 590 MW of power, but locking in battery hardware years before commercial operation creates significant operational exposure for X-ELIO. Canadian Solar said shipments are already underway even as completion remains targeted for late in the decade across Texas and New South Wales. Delivering equipment so far ahead of grid connection risks hardware degradation and warranty expiration before the systems can shift solar generation into evening demand peaks. Can e-STORAGE maintain full battery performance under its long-term service agreements if prolonged staging damages the cells before commercial operation begins?