Renewable Properties to Build 4 MW Fleet Charging Depot in Richmond

Key Facts
  • Renewable Properties secured a $20 million credit facility and $3 million Bay Area Air District grant for the project.
  • The Goodrick Avenue EV Depot will have 60 charging stalls: 16 Level-3 DC fast chargers (up to 350 kW) and 48 Level-2 AC chargers.
  • Construction begins Q2 2026 with completion targeted for October 2027.
  • Site is located near the I-80/I-580 junction in Richmond, serving public agencies, school districts, and municipalities.
  • Renewable Properties develops small-scale utility, community solar, energy storage, and EV infrastructure projects.

Developer and investor Renewable Properties has closed on a land purchase and a $20 million credit facility to build the 4 MW Goodrick Avenue EV Depot, a medium-duty truck fleet charging hub in Richmond, California, according to EV Infrastructure News and North American Clean Energy. Construction is slated to begin in the second quarter of 2026, with completion targeted for October 2027.

What Was Announced

The depot will feature 60 charging stalls — 16 Level 3 DC fast chargers capable of delivering between 50 kW and 350 kW, plus 48 Level 2 AC chargers, the company said. The $20 million credit facility was raised from an unnamed “prominent family office investment firm” and is earmarked for Renewable Properties’ growing EV charging hub division. Renewable Properties also received a $3 million grant from the Bay Area Air District to help construct the project.

The site sits in an industrial infill area of Richmond known for warehousing, distribution, and manufacturing, near the junction of Interstates 80 and 580, positioning it as a regional hub for public agencies, school districts, and municipalities operating in the San Francisco Bay Area. Renewable Properties said it expects additional grid-connection capacity committed from PG&E in 2026 that would let it increase the site’s capacity beyond the initial 4 MW. The company designs the facility for delivery trucks, box trucks, utility service vehicles, and smaller buses under a charging-as-a-service model similar to a power purchase agreement.

Why It Matters

California’s Advanced Clean Fleets Regulation mandates the transition of public fleets to zero-emission vehicles, and depots like Goodrick Avenue supply the charging capacity those fleets need to comply. “This launch will not only expand Bay Area EV fleet infrastructure, it will help lead a shift toward reducing diesel and gas emissions in high traffic corridors and support the health of disadvantaged communities,” said Aaron Halimi, founder and president of Renewable Properties. Dr. Philip Fine, executive officer of the Bay Area Air District, called it “the kind of infrastructure investment we need to help fleets meet zero-emission requirements while delivering cleaner air to communities that have faced the brunt of transportation pollution.” Richmond is designated an Energy Community, Low-Income Community, and Disadvantaged Community.

Critical Perspective

The project is funded and sited but not yet built, and its full value depends on factors outside Renewable Properties’ control. The expansion beyond 4 MW hinges on PG&E committing additional capacity in 2026 — interconnection timelines that have routinely slipped for utility-scale and fleet-charging projects alike. Demand is also policy-driven: the depot’s utilization assumes public and commercial fleets electrify on the Advanced Clean Fleets schedule, a regulation that has faced legal and political headwinds. Until trucks are plugging in, the 60 stalls and 4 MW remain a plan backed by a $20 million facility and a $3 million grant rather than delivered charging throughput.

Sources

Related Coverage

On the Ground
LocationRichmond, CA
UtilityPG&E
GridCAISO
StageFunded