Trending
5 sources Wolfspeed holds a conditional letter for up to $1.5 billion from the Department of War's Office of Strategic Capital, but the first dollar waits on Congress, a note…
3 sources Oracle told Project Jupiter's developer it may defer payments after an Energy Transfer pipeline serving the 2.45 GW New Mexico campus slipped to February 2027.
4 sources CenterPoint Energy submitted more than 17 GW of large load projects into the ERCOT Batch Zero screening and raised its 10-year capital plan by $1.2 billion, a gap…
4 sources ERCOT found four data center and crypto groups that failed voltage ride-through tests, each able to trip more than 5,000 MW and trigger cascading outages.