NRG Lines Up a $3.2 Billion 1.2 GW Texas Gas Plant Paid by Capacity, Not by Data Center Output

Key Facts
  • Plant Capacity: 1.2 GW combined cycle
  • Capital Cost: $3.2 billion
  • Build Cost: $2,700 per kW
  • Contract Term: 15 years minimum
  • Target Operation: late 2029

NRG Energy has agreed on principal commercial terms with an unnamed global cloud and AI hyperscaler. The deal covers a 1.2 GW combined-cycle gas plant in Texas. The Houston company disclosed it on August 4 with its second-quarter results. NRG puts the cost at $3.2 billion, or roughly $2,700 per kW. It targets commercial operation in late 2029. The contract runs a minimum of 15 years. A parent-company guarantee from the customer backs it. More than 95% of project free cash flow comes from capacity payments, not from how much power the data center draws.

“Put simply, we’re paid for the megawatts we build and make available, not for how much the data center runs,” President and CEO Robert Gaudette told analysts. NRG expects the plant to add at least $500 million of annual adjusted EBITDA. It also expects about $375 million of annual free cash flow once the plant runs.

Why It Matters

The payment structure is the story, not the megawatts. A merchant gas plant earns money when prices spike. This one earns money for standing ready. The hyperscaler absorbs the price risk and the volume risk. NRG pegs the pretax unlevered return at 12% to 15%. Fuel and operating costs sit outside the capacity stream and get recovered separately.

That design answers a specific political problem. Texas regulators and elected officials keep asking who pays when a data center lands on the grid. Under this contract the customer pays first. No cost reaches existing ratepayers ahead of that. NRG serves about 8 million retail customers, more than 2 million of them in Texas. The company sits on both sides of that question.

What Is Being Built

The plant will serve an expected 1 GW data center load. It will produce more power than the customer needs. NRG designed it to run grid-connected, in island mode, or to move between the two. A second phase would double capacity to 2.4 GW. NRG gave no date for that phase.

NRG has locked up 5.4 GW of turbine and EPC capacity through 2032. A venture with GE Vernova and Kiewit-TIC supplies it. NRG also identified about 2 GW of uprate potential across its PJM gas fleet. Converting simple-cycle units to combined cycle unlocks that capacity. Add the 445 MW of data center agreements already signed, and NRG projects $1.2 billion of contracted free cash flow in 2030.

The Deal Is Not Signed

NRG cautions that the terms are not final. Negotiations continue and land matters remain open. A final investment decision still needs internal approvals. Gaudette gave no schedule for closing.

The timing is awkward. Texas Governor Greg Abbott ordered a pause on new data center interconnections one day before the announcement. The order requires a project-by-project review of power needs, water use and ratepayer impact. ERCOT responded by delaying its Batch Zero large-load interconnection study. Gaudette declined to say whether the pause touches this deal. He argued instead that the policy shift proves the model. A tighter permitting regime favors developers who bring their own generation.

NRG has one recent data point in its favor. The 415 MW T.H. Wharton peaker in northwest Houston reached commercial operation this year. It was the first new-build generation from NRG in nearly a decade. Two more Texas Energy Fund projects remain on schedule and on budget.

MGRID could not independently verify the identity of the hyperscaler. NRG has not named it. The company reports the counterparty only as investment grade.

Critical Perspective

NRG has an agreement in principle with a customer it will not name, for a plant it has not yet committed to build. Negotiations continue, land matters are open, and the final investment decision still needs internal approval. The credit protection behind the whole structure is a parent-company guarantee, and NRG has not named that parent either. Investors are being asked to price a 15-year cash flow against an unnamed counterparty.

The capacity-payment design shifts merchant risk off NRG and onto the customer. That is a real improvement over a speculative build. It also means the payments continue for 15 years whether the AI buildout holds up or not. If the hyperscaler over-forecast its own demand, the guarantee is the only thing standing between NRG and a counterparty that wants out. Nobody has tested one of these guarantees through a downturn yet.

The $2,700 per kW build cost sits at the top of the $2,000 to $3,000 per kW range that recent combined-cycle projects have set. NRG presents that as consistent with the market. Read it the other way and the customer is paying a premium for a turbine slot and a 2029 delivery date, which is what scarcity looks like.

The second 1.2 GW phase has no schedule. NRG says turbine capacity could free up as soon as 2030, which is a supply statement, not a commitment. And Governor Abbott’s interconnection pause is a live risk that Gaudette declined to quantify on the call. Arguing that the policy shift vindicates the strategy is not the same as showing the project clears the new review.

Sources