FCC Adds Foreign-Made Power Inverters to Its Covered List, Freezing New Certifications for Solar and Storage
- FCC Action Date: July 28, 2026
- US Content Threshold: 65 percent, rising to 75 percent by 2028
- Domestic Inverter Supply: About 40 percent of 2027 demand
- US Inverter Capacity by End of 2026: About 40 GW
- Chinese Inverters DOE Inspected: 30, no malicious hardware found
Listen to this article
The Federal Communications Commission barred new equipment authorizations for foreign-produced power inverters on July 28, 2026. The Public Safety and Homeland Security Bureau added the devices to the FCC Covered List through a national security determination. The FCC published it as public notice DA-26-786A1. The action took effect immediately. Any inverter model not already certified now needs a fresh path to market. The solar and battery storage industries lost their main supply route overnight.
The rule covers “connected” inverters. That means units with parts that allow remote control, sensing, data collection, or monitoring over Wi-Fi, cellular, Bluetooth, or similar links. The FCC treats an inverter as foreign-produced when it fails the Buy America Act threshold of 65 percent US content by value. That threshold rises to 75 percent by the end of 2028.
What Is Still Allowed
Already-certified models keep their authorizations. Retailers hold the right to sell approved stock, and installed units stay legal. Hardwired or fully air-gapped inverters with no remote link fall outside the Covered List. Inverters holding a conditional approval from the Department of War or the Department of Homeland Security also stay eligible.
The FCC cited firmware risk. Regulators argued that remote update paths give a foreign adversary a route to shut down arrays. That reasoning overrides a Department of Energy review from January 2026. DOE inspected 30 Chinese inverters and found no malicious hardware.
Enforcement Reality
The bite lands on the certification pipeline, not on installed fleets. A developer whose specified inverter model lacks FCC approval has to pick a new one. In a solar or battery project already sitting in an interconnection queue, that swap restarts the studies. It adds years, not weeks, to a schedule.
Domestic factories cannot absorb the shift. US plants cover roughly 40 percent of combined 2027 solar and battery demand. In 2020 the domestic share sat near 7 percent. The United States tracks toward about 40 GW of annual inverter capacity by the end of 2026. The EIA forecasts 43.4 GW of utility-scale solar additions in 2026 alone.
Why It Matters
The conditional-approval carve-out is the part worth watching. A blanket ban with a discretionary exemption is not a ban. It is a licensing regime. The FCC has published no criteria for who wins a conditional approval.
Industry sources who spoke to Energy-Storage.news asked not to be named. One said the structure gives the administration “more power to pick who gets to import their inverters.” The same source warned it leaves room for approvals granted “on very suspect reasons.”
Project owners face a concrete near-term problem. Equipment already ordered but not yet certified sits in limbo. Procurement teams should confirm the FCC status of every inverter model in their pipeline now. The grandfather clause protects the model, not the purchase order.
Critical Perspective
Domestic plants cover about 40 percent of 2027 solar and battery demand, so the FCC has written a rule the supply chain cannot satisfy for at least two years. The conditional-approval path through the Department of War and Homeland Security is the escape hatch, and a ban with a discretionary exemption tends to become a licensing regime rather than a wall. Huawei Technologies left the US utility inverter market in 2019 under security pressure, and offshore competitors rather than domestic factories absorbed the vacated share within two years. If the same substitution runs again, does a 65 percent content test buy security or just a different foreign supplier?