FERC Approves PJM Fast-Track Interconnection: 10 Projects a Year, 250 MW Minimum, Online Within 3 Years

Key Facts
  • Annual cap: 10 interconnection requests per year
  • Minimum size: 250 MW unforced capacity
  • Review timeline: About 10 months to an interconnection agreement
  • Operation deadline: Online within 3 years
  • Program expiry: End of 2027

The Federal Energy Regulatory Commission on June 9, 2026 approved PJM Interconnection’s Expedited Interconnection Track, a temporary fast lane allowing the grid operator to review up to 10 interconnection requests per year for new or uprated capacity resources of at least 250 MW that come online within three years, Utility Dive reported. PJM expects about 10 months between an expedited filing and a signed generation interconnection agreement, and the process expires at the end of 2027.

What Actually Changed

The EIT is a standalone, time-limited process running alongside PJM’s regular interconnection queue. Eligible proposals must offer a minimum of 250 MW of unforced capacity and be backed by a pledge from a state’s “primary siting authority” — a governor qualifies — supporting expedited siting so the project reaches commercial operation within three years, according to Utility Dive. Requests are accepted on a rolling basis until the annual limit of 10 is reached, PJM said. “The EIT proposal will help address PJM’s near-term resource adequacy needs by establishing a separate, time-limited, expedited interconnection process for a limited number of resources that are able to bring significant capacity onto the system in the near-term,” FERC wrote. PJM President and CEO David Mills said the approval “creates an important pathway for bringing qualified, shovel-ready generation projects of any kind to connect onto the grid within the next three years.”

Why It Matters

The fast track is part of a series of PJM efforts to bring more generation online quickly as growing data center demand outstrips available electricity supplies, per Utility Dive. At the 250 MW floor, a fully subscribed year fast-tracks at least 2.5 GW of capacity. ClearView Energy Partners said PJM could announce the first 10 selected projects in October — two months before the grid operator runs its base capacity auction for the 2029/30 delivery year.

Critical Perspective

Approval came over protests from Vistra, LS Power, the Illinois Commerce Commission, New Jersey utility regulators, clean energy trade groups, and community organizations. FERC rejected Vistra’s argument that the readiness requirements favor utility-affiliated projects, writing that they are “designed to attract ‘shovel-ready’ projects that have the highest probability of successfully proceeding through this limited interconnection process, regardless of whether they are proposed by an independent power producer or affiliated with an LSE.” The commission dismissed as “speculative” concerns that expedited projects will consume grid headroom and leave regular-queue customers with higher network upgrade costs — a question that gets answered empirically once the first cohort connects. The state-pledge requirement also hands governors a gatekeeping role in deciding which projects jump the line, a political filter inside what FERC frames as a technical screen. Commissioner David Rosner leaned into that reality in a concurrence: “public utility commissioners, governors’ offices, and state legislatures are all necessary partners in ensuring that energy infrastructure is built at the pace needed to stay ahead of demand.”