South Dakota Weighs $1.93 Billion of Transmission for Data Centers It Does Not Have

Key Facts
  • Total South Dakota investment: up to $1.93 billion
  • New line mileage: about 160 miles
  • PowerOn Midwest 765 kV segment: about 90 miles, $1.3 billion to $1.7 billion
  • Easements secured on 765 kV route: 81 of 274 parcels
  • Target completion: 2034

Xcel Energy and Otter Tail Power have asked South Dakota regulators to approve about 160 miles of new high-voltage line across the eastern edge of the state, at a combined cost of up to $1.93 billion. Both applications are now before the South Dakota Public Utilities Commission, and both target completion in 2034. The companies say the lines will carry power for new generation and for large customers, naming data centers and other industrial demand. South Dakota has no hyperscale data centers.

The larger of the two is the PowerOn Midwest Project, filed jointly by Xcel Energy and Otter Tail Power. It would run about 90 miles of 765-kilovolt line south from the Big Stone South Substation in Grant County, crossing Deuel and Brookings counties before turning into Minnesota east of Brookings. The application adds roughly 5 miles of 345-kilovolt line and expansions at the Big Stone and Brookings County substations. The South Dakota segment alone is estimated at $1.3 billion to $1.7 billion, with further segments planned across southern Minnesota.

Otter Tail filed the second project on its own. The Big Stone South to Hankinson to Bison line would run 71 miles of 345-kilovolt line north from Big Stone South through Grant and Roberts counties into North Dakota, continuing to a substation west of Fargo. The South Dakota portion carries a $191 million to $229 million estimate.

The Easements Are the Real Schedule

Neither project controls the land it needs. The 765-kilovolt line holds easements on 81 of the 274 parcels it requires in South Dakota, or 30 percent, and it needs a 250-foot right-of-way across all of them. The 5-mile 345-kilovolt segment has 7 of 19. Otter Tail’s separate 345-kilovolt line, which needs a 150-foot corridor, says only that it will work with landowners to obtain rights through voluntary agreements. Its application does not report how many it has. Xcel expects a commission decision in late 2027 or early 2028, which leaves the rest of the decade to acquire the parcels it does not yet hold, build, and energize.

Why It Matters

The demand case and the load are in different places. South Dakota hosts some small data centers, while the hyperscale campuses driving Upper Midwest load growth have landed in North Dakota and Minnesota. That does not make the projects unjustified. A corridor built toward Minnesota serves load wherever it sits on the far end. It does mean South Dakota is being asked to host the corridor for load that has so far chosen other states. How much of the cost lands on South Dakota customers depends on cost allocation the applications do not settle. Intervenors should press on which load forecast the capital estimates rest on, and whether any of that demand is contracted. The commission has scheduled public input meetings in Brookings on October 20 and Milbank on October 21.

Critical Perspective

The weakest part of both applications is not the engineering, it is the demand evidence. The companies point to data centers and other large industrial load, yet South Dakota has attracted none of the hyperscale campuses that landed in North Dakota and Minnesota. A permit decision expected in late 2027 or early 2028, against a 2034 in-service date, means the commission is being asked to approve up to $1.93 billion on a forecast that will not be tested for years. The easement position sharpens the question. Holding 81 of 274 parcels on the 765-kilovolt route is not a late-stage project, and Otter Tail’s separate filing does not disclose its own count at all. Regulators should ask what happens to South Dakota landowners and ratepayers if the anchor load never arrives on this side of the Minnesota border.